How much time does it take to install a solar PV system?

It takes about 2-4 weeks to install a smaller system and about 4-8 weeks for larger systems. However, the actual construction time at the site is much lower since almost half of the time is spent on off-site activities such as design, engineering, procurement, etc. In certain cases, there may be variations to these timelines on account of access to the site, rains, etc.

 